DrainageCalculators

Retention & Detention Pond Design

Retention (wet) ponds keep a permanent pool that treats runoff; detention (dry) ponds store runoff and drain. Size the pool, storage and outlet step by step.

8 calculators recommended for this problem

Need a number now? Start with preliminary detention storage and outlet sizing, then return here for the full routing, safety, and maintenance workflow.

Size a detention pond

Retention pond vs. detention pond

A retention pond (wet pond) holds a permanent pool that stays full between storms. Runoff from each storm pushes out pool water, and sediment and nutrients settle, so its main job is water-quality treatment. A detention pond (dry pond) stores runoff for a short time and releases it through a restricted outlet until it is empty, so its main job is peak-flow control.

Most retention ponds do both. The permanent pool is sized for the water-quality volume, and detention storage above it holds post-development peaks to the allowed release. An orifice or riser controls that storage, and an emergency spillway passes the largest storm.

Terms vary by state. Florida calls permanently wet ponds that release through an outlet wet detention systems, and uses retention for storage that does not discharge to surface water. Use the definitions in the manual you design to.

How a retention pond is sized: three stacked volumes

Size the pond from the bottom up. Each layer has its own design storm and its own control.

1. Permanent pool = water-quality volume

The Simple Method, as written in the Maryland manual, gives the runoff from the 90% storm:

WQv is in ac-ft, P is the rainfall depth in inches (Maryland uses 1.0 in east and 0.9 in west), A is in acres and I is percent impervious. A standard wet pond holds all of it below the outlet, with a forebay at each inlet.

2. Detention storage above the pool

The pool is already full when a storm starts, so flood storage must sit above it. On small sites the Virginia critical-storm-duration method (VDOT Eq. 11.4) gives a first estimate:

V is in ft³, Qi = C·i·A for a storm of duration Td (min), and qo is the allowable release. Try several durations and keep the largest volume, then confirm it by routing.

3. Outlet, spillway and freeboard

An orifice at the normal pool sets the pool level and limits the release:

h is the head on the orifice centroid, and Cd is about 0.6. Weirs or riser openings higher up handle larger storms. An emergency spillway passes the extreme flood, often with the principal outlet assumed blocked, and freeboard sits above that.

Preliminary design workflow

  1. Confirm design events, allowable releases, volume and water-quality objectives, and downstream constraints.
  2. Screen site soils, groundwater, topography, land take, discharge point, and maintenance access.
  3. Develop existing- and proposed-condition inflow hydrographs for every required event.
  4. Build stage-storage and stage-discharge relationships for the basin and all outlet components.
  5. Route each hydrograph, iterate the storage/outlets, then check the auxiliary spillway and exceedance route.
  6. Document inspection, sediment removal, blockage response, safe access, and long-term ownership.

Design criteria to bring to the tools

  • Approved inflow hydrographs and target release rates
  • Surveyed stage-area or stage-storage data
  • Outlet geometry, elevations, tailwater, and blockage assumptions
  • Maximum acceptable water levels, freeboard, drawdown, and emergency conditions
  • Local stormwater, dam-safety, environmental, and ownership requirements

Workflow follows FHWA HEC-22 Fourth Edition, Chapter 10. Local criteria control the project-specific numeric requirements.

Typical wet-pond geometry

These values come from the Maryland manual and a county manual based on Georgia's. Your manual's numbers govern, and a dam-safety review may add more.

Item Typical requirement (source)
Contributing drainage area 10 acres minimum, 25 acres or more preferred, unless groundwater keeps the pool wet (Maryland). Georgia-based manuals set 25 acres for wet ponds unless a water balance shows the pool will hold. MD 3.1.1; Knox Co. 4.3.1
Permanent pool volume All of the WQv for a standard wet pond. A wet extended-detention pond can hold part of it as extended detention above the pool. MD 3.1 (P-2, P-3)
Sediment forebay At each major inlet; 0.1 in of runoff per impervious acre. Its volume counts toward the WQv. MD 3.1.2, 3.1.3
Pool depth 3–4 ft minimum and 8 ft maximum; deeper pools stratify and go anoxic. Knox Co. 4.3.1
Flow path Length-to-width 1.5:1 or longer; more than 3:1 is better. MD 3.1.4; Knox Co. 4.3.1
Interior side slopes 3:1 (h:v) or flatter, ending on a safety bench. MD 3.1.6
Benches around pools 4 ft or deeper Safety bench (6% maximum slope) plus aquatic bench (18 in maximum depth), 15 ft combined width. Waivable where slopes are 4:1 or flatter. MD 3.1.5, 3.1.6
Low-flow orifice 3 in minimum with an external trash rack. MD 3.1.6
Freeboard 1 ft above the 10-year high water (Maryland ponds exempt from MD-378 review) or 1 ft above the extreme-flood water surface (Georgia-based manuals). MD 3.1.1; Knox Co. 4.3.1
Pond drain A valved drain that can empty the pond within 24 hours. MD 3.1.6

MD = Maryland Stormwater Design Manual (2000, rev. 2009), Vol. I, section number. Knox Co. = Knox County, Tennessee Stormwater Management Manual, Vol. 2, §4.3.1, adapted from the Georgia manual. Full references are at the end of this page.

Worked example: a wet pond for a 10-acre site

Site and design criteria

  • 10.0 acres drain to one pond. After development the site is 50% impervious (roofs, drives, parking) and 50% lawn on clay soil.
  • Water quality: hold the whole WQv in a permanent pool (standard wet pond), with P = 1.0 in.
  • Peak control: keep the post-development 10-year peak at or below the pre-development peak.
  • Extreme flood: pass the 100-year peak over an emergency spillway with at least 1 ft of freeboard.
  • Rainfall: NOAA Atlas 14 10-year intensities for Atlanta, the same data as the IDF curves reference. Use your site's values.

These criteria illustrate the method and follow the pattern of the Maryland manual. Your jurisdiction sets the events, depths and methods.

Step 1. Water-quality volume and forebay

Rv = 0.05 + 0.009 × 50 = 0.50. WQv = 1.0 × 0.50 × 10 / 12 = 0.417 ac-ft (18,150 ft³). The forebay holds 0.1 in over the 5.0 impervious acres, which is 1,815 ft³. That volume is part of the pool, not extra to it.

Step 2. Peak flows (Rational Method)

  • Before development: C = 0.20 (grass on clay soil, 2–7% slope; HEC-22 Table 3-1 gives 0.18–0.22), tc = 30 min, i = 3.37 in/hr. Qpre = 0.20 × 3.37 × 10 = 6.74 cfs. This is the allowable release.
  • After development: C = 0.5 × 0.90 + 0.5 × 0.20 = 0.55, tc = 15 min, i = 4.60 in/hr. Qpost = 25.3 cfs, almost four times the allowable release.

Step 3. Detention storage above the pool

Apply VDOT Eq. 11.4 with tc = 15 min and qo = 6.74 cfs at each Atlas 14 duration. A longer storm has a lower peak but more volume, so the storage peaks at an intermediate duration:

Storm duration Td 10-yr intensity Inflow peak Qi Storage V
15 min 4.60 in/hr 25.3 cfs 20,900 ft³
30 min 3.37 in/hr 18.5 cfs 26,900 ft³
60 min 2.18 in/hr 12.0 cfs 29,200 ft³
120 min 1.34 in/hr 7.37 cfs 25,900 ft³

The 60-minute storm governs: 29,200 ft³ (0.67 ac-ft). On a smooth IDF curve through the 15- and 60-minute values, storage peaks at about 56 minutes with the same volume (VDOT Eq. 11.5). A single triangular hydrograph at tc (VDOT Eq. 11.3, base 2tc) gives only 16,700 ft³, 43% less. Preliminary methods can disagree this much, which is why you check several durations and then route.

Step 4. Basin geometry

Try a bottom of 85 × 20 ft at elevation 99.0, with 4:1 interior side slopes. Slopes that flat let Maryland waive the benches. Set the normal pool at 104.0, giving a 5-ft pool.

  • Permanent pool: 21,700 ft³, at least the 18,150 ft³ WQv, with some room for sediment. The pool surface is 125 × 60 ft (7,500 ft²), a 2.1:1 flow path.
  • Detention zone, 104.0 to 107.0: 29,700 ft³, at least the 29,200 ft³ needed. The water surface at the crest is 12,520 ft², about 2.9% of the site before the embankment and access.

Volumes use the prismoidal formula for a rectangular basin. The average-end-area method agrees within 0.1% on 0.5-ft slices but runs high on coarse ones (about 6% for the pool taken as one 5-ft slice).

Worked-example pond cross-section Schematic long section, not to scale. Pool bottom at 99.0, normal pool and 12-inch orifice invert at 104.0, emergency spillway crest at 107.0, 100-year spillway water surface at 107.94, and top of embankment at 109.0. A forebay berm separates the inlet cell. 100-yr spillway water surface 107.94 Spillway crest 107.0 · routed 10-yr peak 106.83 Detention storage 29,700 ft³ Normal pool 104.0 = orifice invert Permanent pool 21,700 ft³ (WQv 18,150 ft³) Bottom 99.0 Forebay Inlet 12-in orifice Top 109.0
Schematic long section, not to scale (vertical exaggerated). Benches, riser and reverse-slope intake are omitted. The 20-ft emergency spillway is cut through the embankment at 107.0.

Step 5. Size the outlet orifice

The orifice invert sits at the normal pool, so it sets the pool level. For 6.74 cfs at the stage that holds 29,200 ft³ (about 106.96), with Cd = 0.6 and the head measured to the centroid, the orifice equation gives D = 12.8 in. Round down to a 12-in orifice so the release stays under the limit. It passes 5.98 cfs with the water at the crest. You can check the orifice in the Pond Sizing calculator (2.42 ft of head on the centerline).

Stage-storage-discharge above the normal pool, 12-in orifice at 104.0
Stage (ft) Surface area (ft²) Storage above pool (ft³) Orifice outflow (cfs)
104.0 7,500 0 0.00
104.5 8,260 3,940 0.87
105.0 9,040 8,260 2.67
105.5 9,860 12,990 3.78
106.0 10,720 18,130 4.63
106.5 11,600 23,710 5.35
107.0 12,520 29,740 5.98

Below the crown (105.0) the orifice runs part-full, so the table uses the wetted area and the head on its centroid.

Step 6. Route the storms to confirm

Route each Modified Rational hydrograph through the table with level-pool (Modified Puls) routing. Each hydrograph rises over tc, holds Qi until Td, then falls over tc.

Storm duration Inflow peak Routed peak outflow Peak stage
15 min 25.3 cfs 4.67 cfs 106.02
30 min 18.5 cfs 5.50 cfs 106.62
60 min 12.0 cfs 5.77 cfs 106.83
120 min 7.37 cfs 5.43 cfs 106.56

The 60-minute storm is still the worst case. The peak outflow is 5.77 cfs, under the 6.74 cfs limit. The peak stage is 106.83, 0.17 ft below the crest, using 27,600 ft³. Here the Step 3 estimate was a little conservative. The routing sets the final size, not the estimate. The Level-Pool Routing calculator runs the same check for one hydrograph at a time.

Step 7. Emergency spillway and freeboard

For the 100-year Rational peak, apply the frequency factor Cf = 1.25 that some agencies use (HEC-22 Sec. 3.2.2.1; FHWA does not endorse it): Q100 = (1.25 × 0.55) × 6.92 × 10 = 47.6 cfs. Assume the orifice is blocked. A 20-ft broad-crested spillway at 107.0, with C = 2.6 from the low end of the usual range, carries it at H = (47.6 / (2.6 × 20))2/3 = 0.94 ft. That puts the water surface at 107.94. A top of embankment at 109.0 leaves 1.06 ft of freeboard, which meets both 1-ft rules in the table above. Size other spillway shapes with the weir calculator.

Result

A 5-ft permanent pool (21,700 ft³) with 3 ft of detention above it (29,700 ft³). A 12-in orifice at 104.0 controls the outflow, a 20-ft emergency spillway sits at 107.0, and the embankment top is at 109.0.

Not covered here: channel-protection extended detention (Maryland's 1-year, 24-hour storm), other required events, and a water balance. At 10 acres the site meets Maryland's minimum but not the 25 acres Georgia-based manuals expect. Also not covered: embankment, geotechnical and dam-safety design, outlet protection, the pond drain and maintenance access.

Detention pond design software

Final design means routing every required storm through a stage-storage-discharge relationship with a multi-stage outlet. These programs do that:

  • USACE HEC-HMS (free). A reservoir element takes elevation-storage data and outlet structures (orifices, culverts, spillways) and routes the hydrographs from HEC-HMS's own rainfall-runoff models. HEC-HMS tutorials
  • EPA SWMM (free). Storage units connect through orifice, weir and outlet links. Dynamic-wave routing handles tailwater and backwater at the outlet. SWMM tutorials
  • NRCS WinTR-20 (free). Routes NRCS hydrographs through structures described by stage-discharge-storage tables. It fits manuals that require TR-55 and TR-20 methods.
  • Commercial packages. HydroCAD and Bentley PondPack, for example, run the same level-pool routing. They add stage-storage builders, outlet editors and report formats.

For preliminary numbers before you build a model, use the free calculators on this site:

Every tool needs the same inputs: approved inflow hydrographs, a stage-storage table, outlet geometry and tailwater. The worked example is small enough to check by hand or in a spreadsheet.

Frequently asked questions

What is the difference between a retention pond and a detention pond?

A retention (wet) pond keeps a permanent pool between storms and treats runoff by settling. A detention (dry) pond stores runoff for a short time and releases it through a restricted outlet until it is empty. Most retention ponds also have detention storage above the pool, so one basin does both jobs.

How big does a retention pond need to be?

The permanent pool holds the water-quality volume, WQv = P × Rv × A / 12. The detention storage above it comes from routing each design storm through the outlet. In the worked example, a 10-acre site at 50% impervious needs a pool of at least 0.42 ac-ft and gets 0.68 ac-ft of detention above it. Its water surface at the spillway crest covers about 2.9% of the site, before the embankment and access road.

How deep should a retention pond be?

Georgia-based manuals ask for a permanent pool at least 3–4 ft deep and no deeper than about 8 ft. Maryland requires safety and aquatic benches around pools 4 ft or deeper, but lets them be waived where the side slopes are 4:1 or flatter. Detention storage and freeboard sit on top of the pool. The worked example uses a 5-ft pool, 3 ft of detention and 2 ft more to the top of the embankment.

Can I use the Rational Method to size a detention pond?

Only for small sites, and only where your manual allows it. Roanoke, Virginia, for example, allows the Modified Rational Method only for drainage areas under 20 acres with a time of concentration under 20 minutes. Maryland requires TR-55 and TR-20, or an approved equivalent, for its peak-control criteria. When you do use it, check a range of storm durations, not just the one equal to tc.

What software do engineers use to design detention ponds?

The free agency programs are USACE HEC-HMS, EPA SWMM and NRCS WinTR-20. Commercial packages such as HydroCAD and Bentley PondPack do the same level-pool routing with built-in stage-storage and outlet editors. For a first estimate before modeling, use the calculators on this page.

Sources

  1. Maryland Department of the Environment, 2000 Maryland Stormwater Design Manual, Vol. I (rev. 2009): Ch. 2, Unified Stormwater Sizing Criteria (Sec. 2.1 WQv) and Ch. 3, Sec. 3.1 Stormwater Ponds.
  2. Virginia Department of Transportation, Drainage Manual, Ch. 11 Stormwater Management, Sec. 11.5.4, Eqs. 11.3–11.5 and sample problem.
  3. City of Roanoke, Virginia, Stormwater Management Design Manual, Ch. 5, Sec. 5.4.3 and 5.5.2 (Modified Rational Method limits and hydrograph).
  4. Knox County, Tennessee, Stormwater Management Manual, Vol. 2, Sec. 4.3.1 Stormwater Ponds.
  5. NOAA Atlas 14, Vol. 9, Ver. 2, point precipitation-frequency estimates, Atlanta Hartsfield-Jackson airport (partial-duration series).
  6. FHWA, Urban Drainage Design Manual (HEC-22, 3rd ed., 2009), Table 3-1 (runoff coefficients) and Sec. 3.2.2.1 (frequency factors). See the HEC-22 reference.
  7. South Florida Water Management District, ERP Applicant's Handbook, Vol. II (June 28, 2024), Sec. 2.1.17 (wet detention systems).

Recommended Calculators

These tools are most useful for solving "retention & detention pond design" problems.

Detention Pond Sizing Calculator

Estimate preliminary detention pond storage with the Modified Rational Method and size orifice or weir outlets from watershed and allowable-release criteria; use level-pool routing for final design.

Contractor-ready Open

Level Pool Routing Calculator

Enter an inflow hydrograph plus stage-storage and stage-discharge data to route a level pool with the Modified Puls method and return the outflow hydrograph, peak attenuation, maximum stage, and storage.

Engineer-grade Open

Storage Volume Calculator

Estimate preliminary detention storage with either a Modified Rational peak-flow approximation or one selected quick method (Baker, FAA, or simplified) using that method's inputs.

Contractor-ready Open

Rational Method Calculator

Enter runoff coefficient, rainfall intensity, drainage area, and return period to calculate Rational Method peak discharge (Q = CiA), adjusted C, and a transparent calculation breakdown.

Contractor-ready Open

Time of Concentration Calculator

Enter watershed length, slope, cover, and method-specific parameters to calculate time of concentration with Kirpich, FAA, NRCS Lag, Kerby-Hathaway, or TR-55 segmental methods.

Contractor-ready Open

Weir Calculator

Calculate discharge or solve for head for rectangular, Cipolletti, four V-notch, broad-crested, and irregular weirs using the FHWA Hydraulic Toolbox coefficients and irregular-profile workflow.

Contractor-ready Open

Underground Detention Calculator

Design underground detention systems for stormwater management. Calculates storage volume, outlet sizing, and drawdown time per ASCE MOP 77 and FHWA HEC-22 methodology.

Contractor-ready Open

Cistern Sizing Calculator

Calculate cistern sizing for rainwater harvesting. Determines collection potential, storage requirements, and annual water balance using ASABE S597.1 and ARCSA guidelines.

Great for homeowners Open

Looking for a different problem?