Retention (wet) ponds keep a permanent pool that treats runoff; detention (dry) ponds store runoff and drain. Size the pool, storage and outlet step by step.
8 calculators recommended for this problem
Need a number now? Start with preliminary detention storage and outlet sizing, then
return here for the full routing, safety, and maintenance workflow.
A retention pond (wet pond) holds a permanent pool that stays
full between storms. Runoff from each storm pushes out pool water, and sediment and nutrients
settle, so its main job is water-quality treatment. A
detention pond (dry pond) stores runoff for a short time and releases it through
a restricted outlet until it is empty, so its main job is peak-flow control.
Most retention ponds do both. The permanent pool is sized for the water-quality volume, and
detention storage above it holds post-development peaks to the allowed release. An orifice
or riser controls that storage, and an emergency spillway passes the largest storm.
Terms vary by state. Florida calls permanently wet ponds that release through an outlet
wet detention systems, and uses retention for storage that does not discharge
to surface water. Use the definitions in the manual you design to.
How a retention pond is sized: three stacked volumes
Size the pond from the bottom up. Each layer has its own design storm and its own control.
1. Permanent pool = water-quality volume
The Simple Method, as written in the Maryland manual, gives the runoff from the 90% storm:
WQv=12PRvA
Rv=0.05+0.009I
WQv is in ac-ft, P is the rainfall depth in inches (Maryland uses 1.0 in east and
0.9 in west), A is in acres and I is percent impervious. A standard wet pond holds all of it
below the outlet, with a forebay at each inlet.
2. Detention storage above the pool
The pool is already full when a storm starts, so flood storage must sit above it. On small
sites the Virginia critical-storm-duration method (VDOT Eq. 11.4) gives a first estimate:
V=60[QiTd+4Qitc−2qoTd−43qotc]
V is in ft³, Qi = C·i·A for a storm of duration Td (min), and qo is the allowable release. Try several durations and keep the largest volume, then confirm
it by routing.
3. Outlet, spillway and freeboard
An orifice at the normal pool sets the pool level and limits the release:
Q=CdA2gh
h is the head on the orifice centroid, and Cd is about 0.6. Weirs or riser openings
higher up handle larger storms. An emergency spillway passes the extreme flood, often with the
principal outlet assumed blocked, and freeboard sits above that.
Preliminary design workflow
Confirm design events, allowable releases, volume and water-quality objectives, and
downstream constraints.
Screen site soils, groundwater, topography, land take, discharge point, and maintenance
access.
Develop existing- and proposed-condition inflow hydrographs for every required event.
Build stage-storage and stage-discharge relationships for the basin and all outlet
components.
Route each hydrograph, iterate the storage/outlets, then check the auxiliary spillway
and exceedance route.
These values come from the Maryland manual and a county manual based on Georgia's. Your
manual's numbers govern, and a dam-safety review may add more.
Item
Typical requirement (source)
Contributing drainage area
10 acres minimum, 25 acres or more preferred, unless groundwater keeps the pool wet (Maryland). Georgia-based manuals set 25 acres for wet ponds unless a water balance shows the pool will hold. MD 3.1.1; Knox Co. 4.3.1
Permanent pool volume
All of the WQv for a standard wet pond. A wet extended-detention pond can hold part of it as extended detention above the pool. MD 3.1 (P-2, P-3)
Sediment forebay
At each major inlet; 0.1 in of runoff per impervious acre. Its volume counts toward the WQv. MD 3.1.2, 3.1.3
Pool depth
3–4 ft minimum and 8 ft maximum; deeper pools stratify and go anoxic. Knox Co. 4.3.1
Flow path
Length-to-width 1.5:1 or longer; more than 3:1 is better. MD 3.1.4; Knox Co. 4.3.1
Interior side slopes
3:1 (h:v) or flatter, ending on a safety bench. MD 3.1.6
Benches around pools 4 ft or deeper
Safety bench (6% maximum slope) plus aquatic bench (18 in maximum depth), 15 ft combined width. Waivable where slopes are 4:1 or flatter. MD 3.1.5, 3.1.6
Low-flow orifice
3 in minimum with an external trash rack. MD 3.1.6
Freeboard
1 ft above the 10-year high water (Maryland ponds exempt from MD-378 review) or 1 ft above the extreme-flood water surface (Georgia-based manuals). MD 3.1.1; Knox Co. 4.3.1
Pond drain
A valved drain that can empty the pond within 24 hours. MD 3.1.6
MD = Maryland Stormwater Design Manual (2000, rev. 2009), Vol. I, section number. Knox Co. =
Knox County, Tennessee Stormwater Management Manual, Vol. 2, §4.3.1, adapted from the
Georgia manual. Full references are at the end of this page.
Worked example: a wet pond for a 10-acre site
Site and design criteria
10.0 acres drain to one pond. After development the site is 50% impervious (roofs, drives, parking) and 50% lawn on clay
soil.
Water quality: hold the whole WQv in a permanent pool (standard wet pond), with P = 1.0 in.
Peak control: keep the post-development 10-year peak at or below the pre-development
peak.
Extreme flood: pass the 100-year peak over an emergency spillway with at least 1 ft of
freeboard.
Rainfall: NOAA Atlas 14 10-year intensities for Atlanta, the same data as the IDF curves reference. Use your site's values.
These criteria illustrate the method and follow the pattern of the Maryland manual. Your
jurisdiction sets the events, depths and methods.
Step 1. Water-quality volume and forebay
Rv = 0.05 + 0.009 × 50 = 0.50. WQv =
1.0 × 0.50 × 10 / 12 = 0.417 ac-ft (18,150 ft³). The forebay holds 0.1 in over the 5.0 impervious acres, which is 1,815 ft³. That volume is part of the pool, not extra to it.
Step 2. Peak flows (Rational Method)
Before development: C = 0.20 (grass on clay soil, 2–7% slope; HEC-22 Table
3-1 gives 0.18–0.22), tc = 30 min, i = 3.37 in/hr. Qpre = 0.20 × 3.37 × 10 = 6.74 cfs. This is the allowable release.
After development: C = 0.5 × 0.90 + 0.5 × 0.20 = 0.55, tc = 15 min, i = 4.60 in/hr. Qpost = 25.3 cfs, almost four
times the allowable release.
Step 3. Detention storage above the pool
Apply VDOT Eq. 11.4 with tc = 15 min and qo = 6.74 cfs at each Atlas 14 duration. A longer storm has a lower peak but more volume, so the storage
peaks at an intermediate duration:
Storm duration Td
10-yr intensity
Inflow peak Qi
Storage V
15 min
4.60 in/hr
25.3 cfs
20,900 ft³
30 min
3.37 in/hr
18.5 cfs
26,900 ft³
60 min
2.18 in/hr
12.0 cfs
29,200 ft³
120 min
1.34 in/hr
7.37 cfs
25,900 ft³
The 60-minute storm governs: 29,200 ft³ (0.67 ac-ft). On a smooth IDF curve through the 15- and 60-minute values, storage peaks at about 56 minutes with the same volume (VDOT Eq. 11.5). A single triangular hydrograph at tc (VDOT Eq. 11.3, base 2tc) gives only 16,700 ft³, 43% less. Preliminary methods can disagree this much, which is why you check several
durations and then route.
Step 4. Basin geometry
Try a bottom of 85 × 20 ft at elevation 99.0, with 4:1 interior side slopes. Slopes that flat let Maryland waive
the benches. Set the normal pool at 104.0, giving a 5-ft pool.
Permanent pool: 21,700 ft³, at least the 18,150 ft³ WQv, with some room for sediment. The pool surface is 125 × 60 ft (7,500 ft²), a 2.1:1 flow
path.
Detention zone, 104.0 to 107.0: 29,700 ft³, at least the 29,200 ft³ needed. The water surface at the crest is
12,520 ft², about 2.9% of the site
before the embankment and access.
Volumes use the prismoidal formula for a rectangular basin. The average-end-area method
agrees within 0.1% on 0.5-ft slices but runs high on coarse ones (about 6% for the pool
taken as one 5-ft slice).
Schematic long section, not to scale (vertical exaggerated). Benches, riser and
reverse-slope intake are omitted. The 20-ft emergency spillway is
cut through the embankment at 107.0.
Step 5. Size the outlet orifice
The orifice invert sits at the normal pool, so it sets the pool level. For 6.74 cfs at the stage that holds 29,200 ft³ (about 106.96), with Cd = 0.6 and the head measured to the centroid, the orifice equation gives
D = 12.8 in. Round down to a 12-in orifice so the release stays under the limit. It passes 5.98 cfs with
the water at the crest. You can check the orifice in the Pond Sizing calculator (2.42 ft of head on the centerline).
Stage-storage-discharge above the normal pool, 12-in orifice at 104.0
Stage (ft)
Surface area (ft²)
Storage above pool (ft³)
Orifice outflow (cfs)
104.0
7,500
0
0.00
104.5
8,260
3,940
0.87
105.0
9,040
8,260
2.67
105.5
9,860
12,990
3.78
106.0
10,720
18,130
4.63
106.5
11,600
23,710
5.35
107.0
12,520
29,740
5.98
Below the crown (105.0) the orifice
runs part-full, so the table uses the wetted area and the head on its centroid.
Step 6. Route the storms to confirm
Route each Modified Rational hydrograph through the table with level-pool (Modified Puls)
routing. Each hydrograph rises over tc, holds Qi until Td,
then falls over tc.
Storm duration
Inflow peak
Routed peak outflow
Peak stage
15 min
25.3 cfs
4.67 cfs
106.02
30 min
18.5 cfs
5.50 cfs
106.62
60 min
12.0 cfs
5.77 cfs
106.83
120 min
7.37 cfs
5.43 cfs
106.56
The 60-minute storm is still the worst case. The peak outflow is 5.77 cfs, under the 6.74 cfs limit. The peak stage is 106.83, 0.17 ft below the crest, using 27,600 ft³. Here the Step 3 estimate was a little conservative. The routing sets the final size, not
the estimate. The Level-Pool Routing calculator runs the same check for one hydrograph at a time.
Step 7. Emergency spillway and freeboard
For the 100-year Rational peak, apply the frequency factor Cf = 1.25 that some agencies use (HEC-22 Sec. 3.2.2.1; FHWA does not endorse it): Q100 = (1.25 × 0.55) × 6.92 × 10 = 47.6 cfs. Assume the orifice is blocked. A 20-ft broad-crested spillway at 107.0, with C = 2.6 from the low end of the usual range, carries it at H
= (47.6 / (2.6 × 20))2/3 = 0.94 ft. That puts the water surface at 107.94. A top of embankment at 109.0 leaves 1.06 ft of freeboard, which meets both 1-ft rules in the table above. Size other spillway shapes
with the weir calculator.
Result
A 5-ft permanent pool (21,700 ft³) with 3 ft of detention above it (29,700 ft³). A 12-in orifice at 104.0 controls the outflow, a 20-ft emergency spillway sits at 107.0, and the embankment top
is at 109.0.
Not covered here: channel-protection extended detention (Maryland's 1-year,
24-hour storm), other required events, and a water balance. At 10 acres the site meets Maryland's
minimum but not the 25 acres Georgia-based manuals expect. Also not covered: embankment, geotechnical
and dam-safety design, outlet protection, the pond drain and maintenance access.
Detention pond design software
Final design means routing every required storm through a stage-storage-discharge
relationship with a multi-stage outlet. These programs do that:
USACE HEC-HMS (free). A reservoir element takes elevation-storage data and
outlet structures (orifices, culverts, spillways) and routes the hydrographs from HEC-HMS's
own rainfall-runoff models. HEC-HMS tutorials
EPA SWMM (free). Storage units connect through orifice, weir and outlet links.
Dynamic-wave routing handles tailwater and backwater at the outlet. SWMM tutorials
NRCS WinTR-20 (free). Routes NRCS hydrographs through structures described
by stage-discharge-storage tables. It fits manuals that require TR-55 and TR-20 methods.
Commercial packages. HydroCAD and Bentley PondPack, for example, run the same
level-pool routing. They add stage-storage builders, outlet editors and report formats.
For preliminary numbers before you build a model, use the free calculators on this site:
Every tool needs the same inputs: approved inflow hydrographs, a stage-storage table, outlet
geometry and tailwater. The worked example is small enough to check by hand or in a
spreadsheet.
Frequently asked questions
What is the difference between a retention pond and a detention pond?
A retention (wet) pond keeps a permanent pool between storms and treats runoff by settling. A detention (dry) pond stores runoff for a short time and releases it through a restricted outlet until it is empty. Most retention ponds also have detention storage above the pool, so one basin does both jobs.
How big does a retention pond need to be?
The permanent pool holds the water-quality volume, WQv = P × Rv × A / 12. The detention storage above it comes from routing each design storm through the outlet. In the worked example, a 10-acre site at 50% impervious needs a pool of at least 0.42 ac-ft and gets 0.68 ac-ft of detention above it. Its water surface at the spillway crest covers about 2.9% of the site, before the embankment and access road.
How deep should a retention pond be?
Georgia-based manuals ask for a permanent pool at least 3–4 ft deep and no deeper than about 8 ft. Maryland requires safety and aquatic benches around pools 4 ft or deeper, but lets them be waived where the side slopes are 4:1 or flatter. Detention storage and freeboard sit on top of the pool. The worked example uses a 5-ft pool, 3 ft of detention and 2 ft more to the top of the embankment.
Can I use the Rational Method to size a detention pond?
Only for small sites, and only where your manual allows it. Roanoke, Virginia, for example, allows the Modified Rational Method only for drainage areas under 20 acres with a time of concentration under 20 minutes. Maryland requires TR-55 and TR-20, or an approved equivalent, for its peak-control criteria. When you do use it, check a range of storm durations, not just the one equal to tc.
What software do engineers use to design detention ponds?
The free agency programs are USACE HEC-HMS, EPA SWMM and NRCS WinTR-20. Commercial packages such as HydroCAD and Bentley PondPack do the same level-pool routing with built-in stage-storage and outlet editors. For a first estimate before modeling, use the calculators on this page.
FHWA, Urban Drainage Design Manual (HEC-22, 3rd ed., 2009), Table 3-1 (runoff coefficients)
and Sec. 3.2.2.1 (frequency factors). See the HEC-22 reference.